The long-awaited upgrading of Bafeti Learners with Special Educational Needs (LSEN) School in Mabopane is reportedly approaching completion, but outstanding construction and compliance issues continue to raise questions about the project's readiness for occupation.
The Gauteng Department of Infrastructure Development (DID), in its latest progress update, reported that paving, landscaping and other finishing work are underway, with improvements in site housekeeping also observed.
However, several important components remain outstanding, including fire safety installations, liquefied petroleum gas (LP gas), air-conditioning and external facilities.
More concerning are the outstanding issues relating to roof compliance, fire evacuation arrangements, water challenges and municipal approval of the Occupation Certificate.
These requirements are particularly important at a school catering for learners with special educational needs, where accessibility, emergency preparedness and reliable basic services are essential.
A history of construction and compliance concerns
The challenges surrounding the project are not new.
DID inspection reports dating back to October 2025 identified several construction and safety concerns, including missing fire extinguishers and signage, incomplete safety measures, construction rubble and weather-related delays.
At the time, the project was reportedly approximately 49% complete and 14% behind schedule.
Subsequent inspections in December 2025 and February 2026 continued to highlight concerns involving workmanship, roof-truss anchoring, wall flashing, open excavations, fire safety and occupational health and safety compliance.
By October 2026, the Department reported approximately 89% completion and indicated a revised completion deadline of 2 October 2026.
That deadline has passed, yet the latest update continues to identify outstanding work and compliance requirements.
Safety and compliance before occupation
The outstanding roof compliance and fire evacuation issues deserve particular attention.
For learners with disabilities and other specialised support requirements, emergency evacuation arrangements must be appropriate to their individual mobility and accessibility needs.
Fire protection systems, emergency exits, signage and evacuation procedures must be properly assessed before the school is occupied.
The reported water challenges also require a sustainable solution to ensure that the institution can operate effectively.
Furthermore, municipal approval of the Occupation Certificate remains a significant milestone. Construction progress alone does not establish that a building is ready for lawful occupation.
Questions over the missed deadline
The Department's latest communication does not provide a definitive new handover date.
This raises questions about the reasons for the missed October deadline, the extent of outstanding corrective work and whether the contractor has been held accountable for delays.
Capital Daily News believes the public deserves transparency regarding the project's original budget, current expenditure, appointed contractor, contractual timelines and any approved extensions.
DID should also clarify whether the roofing concerns identified during previous inspections have been resolved and independently certified, whether fire safety requirements have been met and what remains outstanding before municipal approval can be secured.
Learners deserve more than construction announcements
The upgrading of Bafeti LSEN School represents an important investment in specialised education infrastructure in Mabopane.
Once completed and formally handed over, the improved facilities are expected to provide learners with a safer and more supportive learning environment.
However, the success of the project must ultimately be measured by the delivery of a fully functional, compliant and accessible school, rather than construction percentages or announcements of progress.
The Department must provide clarity on when the outstanding work will be completed and when learners and educators can expect to benefit from the upgraded facilities.
Capital Daily News will continue monitoring the project and will seek further clarification from the Gauteng Department of Infrastructure Development and the City of Tshwane regarding outstanding compliance matters and the anticipated handover date.
CDN editorial note: Concerns identified in inspection reports are not, by themselves, proof that the building is structurally unsafe or that any party has committed wrongdoing. The relevant authorities and project stakeholders must be given an opportunity to respond.